The Arab Cement Company in Saudi Arabia said that the Rabigh substation expansion project for the high voltage would be delayed until the third quarter of 2021.

The company stated in a disclosure on the Tadawul website that it had received a letter from the Electricity Transmission Company stating that the expected date of completion of the expansion required to implement the Rabigh conversion station expansion project for ultra voltage is 380 volts. / 110 kV. (Source of Nutrition) will be by the third quarter of 2021.

The company explained that the reason for the delay in the completion of the project is due to the delay of the authority responsible for implementing its project, stressing that there is no change in costs and there is no financial impact of the delay.

>